February 15 Update
Work continues on the construction of the West Building and the renovation of the Food Pantry garage bays. Here is what we saw happen this week:
- The underground utility work is completed and the exposed dirt has been covered with straw.
- The sidewalks and roadway are now open.
- The site is completely ready for the modular unit footings crew.
- The green pipes sticking out are sewer pipes.
As always, thank you for your cooperation with this project that greatly expands our ministry on campus. Questions? Contact [email protected].