March 8 Update

This past week saw a lot of progress on the West Building:

  • the footings were dug out and constructed
  • the seven modular units that comprise the West Building were set in place
  • work began on the interior of the units
  • upcoming exterior work will include the entrance ramps and deck skirt

Thank you for your continued prayer and support of this project!